It's now mid March, and the builder was supposed to be finished 2 weeks ago according to their schedule with lots of fluff...hmm...
Needless to say, we've had to severely cut short our expectations, and now we're just hoping and praying that they finish before we leave for our wedding! I CAN see the light at the end of the tunnel, though. We are slowly getting there. The beginning of this past week showed lots of promise. We had stair installation guys, electricians, plumbers, and gyprock guys in all at the same time...it was like a little beehive of activity. And then it crashed...only the closet door people came on Tuesday and the plumbers on Wednesday to install the toilet. I guess I can't complain too much, though...we are getting ever closer. And they have finished some parts enough to allow us to get our own work done. Last weekend, Andy and a friend finished laying the bamboo flooring in the upstairs living area so that the stairs and ballustrading could be installed without causing problems for us later. And I managed to get the future study painted last week as well...so we trudge slowly along...
 |
| The study is painted...only thing left is for the electrician to come and install the power points & lights. |
 |
| Flooring laid in the stair landing area, and the stairs & ballustrading are installed! |
 |
| Finished flooring in the open living area. |
 |
| Toilet installed in the downstairs powder room. Now they just have to patch the hole in the wall and install the sink. |
 |
| Tiling and plumbing in the downstairs bathroom is finished as well. |
 |
| We have closet doors in bed 4! |
 |
| Can you believe how much better this room looks than it did before?!?! Just wait until it's got paint and carpet! |
 |
| Bed 3 has closet doors as well...getting ever closer! |
 |
| Nice LED spotlights for our theatre/billiards room. |
 |
| The opposite view...gotta love that peach door, eh? :) |
 |
| And we've got stairs!!! They look really good...or I think so anyways :) |
 |
| The laundry room has lights now too... |
 |
| Our future walk-in robe covered in preparation for knocking out the doorway to the bedroom. |
 |
| The bedroom covered and prepped as well...it's going to be a massive mess! |
More updates to come shortly, I hope! They say they'll be finished in about 10 days...oh boy, I can't wait! :)